Water Project #7 – complete.
Community: Los Jirones
85 houses, 94 families & 340 people
This was a major project with a lot of difficulties. Terrain was filled with rocks, and we had to review with hydraulic engineers and redirect our plans several times to make this project work.
This community had no running water and now all houses do. We put a mechanical pump into a well, built a water tower, and plumbed water into all houses in this community.
This is the 7th major water project completed. We have completed 1200 houses in total and we’ll over 5000 people now have running water. I am very proud of my team in Nicaragua and my guys @premiumandexotic